Hey Bath · Roads
Second emergency gas works in a month close a Pulteney Bridge lane
In short
A lane on Pulteney Bridge is closed again for emergency gas works, with its lamps reported out for months and a damaged footway at a shopfront.
Wales and West Utilities has closed a lane on Pulteney Bridge for emergency gas works from 10 November. The same company had an emergency lane closure on the bridge from 11 October, which has now ended, making this the second emergency closure on the bridge in a month. We assume the two are separate incidents, as they carry different start dates and the October one has finished; we have not read the utility's own notice.
Buses at the bridge's north end are affected as well. The Laura Place and Edward Street stops will not be served by the U1, U3, 11 and X86 from 10 to 16 November.
The bridge's lamps have been reported out for months. On 6 November a resident reported that all the street lights on Pulteney Bridge had failed, saying none of the wall-mounted lantern-style lamps had worked for at least a couple of months. An earlier report on 22 September said multiple lamps on the bridge and the first lamp on Argyle Street were unlit, making the street unusually dark. On 5 November a resident reported that concrete had come away outside the shopfront of 1-2 Pulteney Bridge because of works, leaving a hazardous gap in the footway.
Antica Pulteney Bridge Restaurant at 5 Argyle Street was granted a pavement licence on 4 November. Tables can be out every day from 10am to 11.30pm.
Two more reports describe water problems in Laura Place. On 21 October a resident reported continued flooding of the pavement on the corner of Laura Place opposite the bridge. On 16 September another resident said the Laura Place fountain had been out of action for at least a month.
Pulteney Bridge is a listed building, according to Historic England's list. The lane closures come from the council's own record of works, which can change. The lighting, footway and flooding items are residents' reports, closed by the council, and are not inspection findings.
Why should residents care?
A lane on the bridge is closed and the bus stops at its north end are out of use until 16 November, so anyone crossing the city centre has to allow for it.
What happens next
The bus stops at the bridge's north end are not served until 16 November, and the council's record of works is where any change to the lane closure will show.
Where this comes from
Every fact in this piece comes from these.
How this was written
Written by the Hey Bath Newsdesk from public records, checked against them, and read by a person on our team. How we write these.
Sources: Roadworks (DfT Street Manager), FixMyStreet (B&NES), Bus disruptions (Bus Open Data Service), Licensing applications (B&NES).
Checked .
Spotted a mistake? Tell us and we’ll correct it here, with the date. All corrections.